5/4/07
quick new project in today.
a trailer to take a tot rod and also a full size motorbike.
set up the jig in the week ready so full steam ahead after work today.
this took about 2 1/2 hours to get to this stage

broke out the new mig welder for this one.
been sat here for ages but as i mostly use tig this was a good opotunity to see what it was like.
think im slowly getting the hang of this welding malarky

6/4/07
managed another 3 hours today and got it mostly wrapped up.
couple of hours welding tommorow then make a tailgate and hook things for the sides.

7/4/07
finished today.
had about 3 hours solid welding on it spred over the day then the rest of the time doing the little bits like hold
downs and rear tailgate and mounting the hardware.
also had a helper today.the trailers owner making some of the bits
a nice leisurely day of fabrication.
paint tommorow

|